ST0014 - Locker buiding and Data Center construction

New Locker Building and Data Center Foundation Construction- Civil Works

Client: Encotec/BP

 

Activities:

  1.        Topographical survey of the area to establish required coordinates and elevations
  2.        Excavation of foundation area
  3.        Backfilling with subbase material and compaction
  4.        Formwork Installation
  5.        Rebar Installation
  6.        Concrete blinding
  7.        Concrete Pouring
  8.        Installation of anchor bolts
  9.        Installation of drainage line